For weeks 27, 28, 29, 30, 31, 32, 33 and 34 the TSOs will not contract FRR-A capacity.
For weeks 35, 36, 37, 38 and 39 the TSOs will contract FRR-A capacity for 05:00-08:00 CET and 19:00-01:00 CET for week days (Monday to Friday).
The TSOs will inform about the adjustments of the national procurement that are needed.
A new market message for FRR-A capacity contracting from week 40 2014 onwards will follow later.
Lysaker, 6 June 2014
For further information, please contact:
Karolina Näsholm, Svenska Kraftnät, +46 8 4758201
Gunnar Nilssen, Statnett, +47 23903238
Vesa Vänskä, Fingrid, +358 40 526 5050