Dear Market Participants,
As communicated yesterday (16/01/2021), there is an increased risk of decoupling due to an unidentified issue. The issue is related to a market clearing point outside of the flow-based domain.
CWE TSOs, Amprion and Elia, yesterday evening informed that the External constraint of ALEGRO will be reduced to the Long-term rights ([-250MW;250MW] therefore Day-ahead flow limited to 250 MW on the interconnector) for Business Day 18/01/2021 as an additional mitigation measure.
See message on JAO: https://www.jao.eu/news/messageboard/view?parameters=%7B%22NewsId%22%3A%22fdb574c1-37ba-45fe-ad50-acb2015c1e4e%22%2C%22FromMoreTSO%22%3A%221%22%7D
Nord Pool desk
T: +47 6710 9110 (Day-ahead desk) | E: dayahead@nordpoolgroup.com |
T: +47 6710 9115 (Intraday desk) | E: intraday@nordpoolgroup.com |